2024
 
Completion of CTEP Phase 65
Awarded of GPRS200 Biomass Plant Structure -- USA
Awarded of CTEP Phase 67 (2 Jackets) -- Gulf of Thailand
Awarded of GRDA Power Plant Structure module (1 Unit) -- USA
Awarded of 4 Offshore Topsides Platform -- Andaman Sea
2023
 
Awarded of CTEP Phase 65 (2 Jackets) -- Gulf of Thailand
Completion of CTEP Phase 61
Completion of CTEP Phase 63
Completion of Kipper Compression Project
2022
 
Awarded for CTEP Phase 63 (2 Jackets) -- Gulf of Thailand
Awarded for Kipper Compression Project (Worley-ExxonMobil) (7 Modules Fabrication) -- Australia
2021
 
Awarded for CTEP Phase 61 (2 Jackets) -- Gulf of Thailand
2020
 
Completed and Sail-away first shipment of BLADE modules
2019
 
Awarded for BLADE Project, Beaumont, USA – Module fabrication
Awarded for CTEP Phase 59
2018
 
Awarded Formosa 1 Phase 2 Offshore Wind Farm Project
2017
 
Awarded GPS Bahrain Regasification Topside Project
2016
 
Awarded CPOC Phase 4 Project
Awarded CTEP Phase 53 Project
Completed Ichthys PAR/PAU modules fabrication 40,000 MT and sail away
2015
 
Awarded for CTEP Phase 51
2014
 
Awarded for CTEP Phase 49-50
2013
 
Awarded for CTEP Phase 47-48
2012
 
Awarded for JKC Ichthys - Onshore module fabrication, Australia
Awarded for CTEP Phase 45-46
Awarded for Carigali-HESS Bulan B Project
2011
 
100th Chevron platform loads out
Largest jacket fabrication and sail away (ESSOL D1)
Awarded for CTEP Phase 43-44
Awarded for IHI Mid Water Arch
2010
 
Awarded for CTEP Phase 41-42
Awarded for Carigali-HESS Suriya B Project
Awarded ONGC - D1 Development Project
2009
 
100th offshore facilities load out
Awarded the PTTEP Arthit 1C Project
Awarded for CTEP Phase 36-37
Awarded for CTEP Phase 39
Awarded for Salamander Bualuang Brownfield
Awarded for CPOC Muda D WHP
2008
 
Awarded for CTEP Phase 35
Awarded for BG India - Hydra PK & SWP Project
2007
 
Awarded for CTEP Phase 33-34
Awarded for COTL Stage 5
Awarded for Pearl Oil (Mubadala) Jasmine D Development
Awarded for Pearl Oil (Mubadala) Banyen A Development
Awarded for CPOC - Phase I Development
Awarded for Reliance - Dhirubhai 1 & 3 Development Project
Awarded for Hindustan PY 1 Development Project
2006
 
Awarded the PTTEP Arthit LQ Emtunga project, the 1st LQ fabricated in Thailand
Awarded for CTEP Phase 32
Awarded for COTL Stage 4
Awarded for COTL Stage BWC
Awarded for Pearl Oil (Mubadala) Jasmine B2 Development
Awarded for Pearl Oil (Mubadala) Jasmine A, B and C Brownfield
Awarded Carigali-HESS - Cakerawala Phase II Development
Awarded for BG NRPOD India
2005
 
Awarded for Unocal - Surat Trunkline
Awarded for Unocal Phase 29-30
Awarded for Unocal - Pailin Pipeline Replacement
Awarded for COTL Stage 3B
Awarded for CTEP Phase 31
Awarded for Pearl Oil (Mubadala) Jasmine B Development
2004
 
Awarded for Unocal Phase 27-28
Awarded for Unocal - Erawan Mercury Removal Platform (ERMRP)
Awarded for COTL Stage 3A
Awarded for Pearl Oil (Mubadala) Jasmine C Development
Awarded for PTTEP WP9 & WP10 Revamp Project
2003
 
Awarded for the Unocal Platong Oil Central Processing Platform II
Awarded for Unocal Phase 25-26
Awarded for Pearl Oil (Mubadala) Jasmine Field Development Phase 1
2002
 
Awarded for Unocal Phase 23-24
Awarded for GSPC- Hazira Offshore Development Project
2001
 
Awarded for Unocal Big-Oil Oil Export System
Awarded for PTT-24’’ Gas Export Pipeline (North Pailin Export Line)
2000
 
Awarded for the Unocal Platong Oil Central Processing Platform, the 1st CPP fabricated in Thailand
Awarded for GSPC- Hazira Offshore Development Project
Awarded for Unocal Phase 21/6
Awarded for Unocal Phase 22